2.1.10 Flood Protection, Water Supply and Sewage Assets

Environment Agency owned and operated assets

During the winter the Devon & Cornwall Asset Performance and MEICA teams carried out several post
event asset inspections to monitor the integrity of the flood defences. The prolonged nationwide event
also prompted the Agency to request military assistance.

Though the storms were focused on the coast, some fluvial assets were also affected by high river
flows and tidal assets by repeated loading. The list below details the assets that were identified as
being affected. Some of these assets are owned by a third party but the Environment Agency took an
active role in assisting with the repair using its  discretionary powers.

  • Flood Bank on the Par river
  • Copperhouse (Hayle) tidal gate
  • Padstow tidal gate
  • Polperro tidal gate
  • Bude Flood Alleviation Scheme raised defences
  • Helston Flood Alleviation Scheme & Loe Bar outlet culvert and associated structures.
  • Mawgan Porth fluvial defences
  • Lower Tamar embankments, including Calstock flood bank
  • Raised defences at Angarrack

In addition to the affected flood defences several watercourses have received extra sediment leading to
restrictions in conveyance at some locations. Plans to dredge these particular areas and recover the
affected assets are underway.

 

Impact of Severe Weather in Cornwall – Winter 2013/2014

Report Date: October 2014 V1.2 D

21

Book page

TitleCreated
240310 | Detailed plans for affordable-led housing in Connor Downs 10th March 1 week 13 hours agoBook page
240310 | Waste collections changes Helston, Penzance, Hayle | second phase:food waste, recycling, rubbish - commences July 1 week 14 hours agoBook page
240218 | Collapsed North Quay development in Hayle described as a 'sea of despair' 3 weeks 5 days agoBook page
240214 | Hayle North Quay development collapse sees eight companies go bust Work has ground to a halt on the blocks of flats 4 weeks 14 hours agoBook page
240220 | Poling works | Grist Lane and Marsh Lane, Angarrack | expected 20 Feb 2024 0830-1630, for one day 5 weeks 6 days agoBook page
231130 | Are you ready for weekly food waste recycling? | Food Waste, Recycling and Rubbish Collection Changes 14 weeks 4 days agoBook page
230821 | People of Cornwall town 'thrown under bus' over housing plan | direct result of councillors handled Hayle masterplan 29 weeks 5 days agoBook page
230817 | When will new rubbish collection changes start, Cornwall 30 weeks 3 days agoBook page
230809 | Holiday park in Cornwall for emergency housing still empty | Sandbank site purchased Cornwall Council in Jan 2022 31 weeks 2 days agoBook page
230811 | Decision on huge solar farm at Carnhell Green: refused 31 weeks 2 days agoBook page
230809 | Nearest NHS dental practice to Cornwall taking new patients 31 weeks 2 days agoBook page
230730 | Practice Comparison: Praze-An-Beeble Surgery; Bodriggy Health Centre | 2023 GP Patient Survey 33 weeks 17 hours agoBook page