240224 | Doomed Hayle North Quay development through the years - in pictures
Doomed Hayle North Quay development through the years - in pictures
Seven aerial pictures show the site throughout the past five years in the wake of the developers going into administration

With work on one of Cornwall's most controversial developments grinding to a halt earlier this month, pictures reveal what the site looked like five years ago before any work had begun - and the progress made since then.
Construction has completely stopped on a block of flats at the site of North Quay in Hayle as administrators were called in on February 7. Eight companies involved in the North Quay development project, including Corinthian Homes, are now in administration.
The construction site is currently locked up and administrators have been seen walking around the site. It's been compared to a "sea of despair" as locals have reacted to the now derelict scenes at the harbour, where at least 44 flats and houses have already been purchased and are now indefinitely surrounded by a construction site.
READ MORE: Eight companies go bust in North Quay development collapse
READ MORE: Collapsed North Quay development in Hayle described as a 'sea of despair'
One of Cornwall's biggest, most high-profile developments in recent years, the North Quay housing scheme site, which includes Hayle's operational harbour, is said to have "entered a new phase". It's as London-based insolvency specialists Moorfields Corporate Recovery was appointed to deal with the fallout.
Now seven images, provided by Cornwall councillor for Hayle Peter Channon, show how the site has evolved since it was first cleared and prepared for development in February 2019 - right up to May of 2023.
"The whole thing is not very good for Hayle and it's going to be a while until it all unravels but we're going through the procedures at the moment and the administrators will make a decision in due course," he told CornwallLive last week. "Its history and heritage are so important to the town. It has done a huge amount for Hayle and Cornwall and deserves a secure, loved future."
He said the circumstances are sad for the area and the town has very much felt "in limbo" for a long time over the development. "From a local point of view, it is just such an intrinsic part of Hayle. But what happened here, we can't control.
"Nothing has ever been normal on this site. It really was never normal so it's not a shock. No one can truly say what's going to happen but the best we can hope for is to get some security back into the equation." Read that full story, here. Scroll down for the photos.
14.2.19

Taken almost five years to the day before the collapse of the North Quay development, this is the first picture taken by Cllr Peter Channon which shows the site cleared and prepared for work
(Image: P CHANNON) 1 of 726.3.20

Just over a year later work was starting to take shape with the first signs of contractors on site, just as the first Covid-19 lockdown hit in the UK.
(Image: P CHANNON) 2 of 722.7.20

There was little progress throughout 2020 with various Covid restrictions in place but beachside café LULA opened this year
(Image: P CHANNON) 3 of 731.8.20
4 of 7
The latter end of 2020 saw work really starting to take shape with the first visible signs of structures and buildings going up.
(Image: P CHANNON)
5.11.20

The first property was sold just a month after this picture was taken, with more exchanging in early 2021.
(Image: P CHANNON)22.2.21

By February the first phase of 17 three-bedroom houses at nine Rew an Borthva was pretty much completed and you can see progress being made on the apartment building Chi an Treth for which properties started selling in June 2022.
(Image: P CHANNON) 6 of 76.5.23

By May 2023 it seems work had slowed significantly on site and while the first phase of flats had sold, the commercial spaces on the ground floor were never completed.
(Image: P CHANNON) 7 of 7
https://archive.ph/dUrzP
- Printer-friendly version
- Login or register to post comments
- Permalink
Contributions
- Angarrack Defibrillator Team (25)
- Angarrack Inn (336)
- Angarrack Methodist Chapel (3)
- AngarrackSanta (2)
- Carol (15)
- Gail (1)
- GordonG (12)
- Hayle Development Group on Facebook (5)
- Hayle Harbour Authority (4)
- Hayle Town Council (5)
- louise (1)
- Lynne (111)
- Mal (1)
- MattBuckley66 (9)
- Neil (22)
- Neils Garden Care (9)
- Russell (21)
- Secretary - Christmas Lights (144)
- Steve (3)
- webmaster (5128)
Book page
tags in
Similar
- 230417 | Hayle North Quay collapsed company Sennybridge leaves £135 million debts
- 240218 | Collapsed North Quay development in Hayle described as a 'sea of despair'
- 240214 | Hayle North Quay development collapse sees eight companies go bust Work has ground to a halt on the blocks of flats
- 210721 | Liverpool stripped of UNESCO World Heritage Site status over waterfront development
- PA20/05161 | Approved with conditions | Reserved Matters application for the construction of 377 residential units; 598 sqm reta
Similar across site
- 230417 | Hayle North Quay collapsed company Sennybridge leaves £135 million debts
- 240224 | Doomed Hayle North Quay development through the years - in pictures
- 240218 | Collapsed North Quay development in Hayle described as a 'sea of despair'
- 240214 | Hayle North Quay development collapse sees eight companies go bust Work has ground to a halt on the blocks of flats
- 210721 | Liverpool stripped of UNESCO World Heritage Site status over waterfront development
Hayle and Angarrack news | Google
- Hayle road closures: 11 streets affected by resurfacing works - Cornwall Live
- Hayle road closures: 11 streets affected by resurfacing works - Cornwall Live
- Hayle road closures: 11 streets affected by resurfacing works - Cornwall Live
- Hayle road closures: 11 streets affected by resurfacing works - Cornwall Live
- 'David and Goliath battle' over waste site in Cornish countryside - Cornwall Live
- 'David and Goliath battle' over waste site in Cornish countryside - Cornwall Live
- 'David and Goliath battle' over waste site in Cornish countryside - Cornwall Live
- 'David and Goliath battle' over waste site in Cornish countryside - Cornwall Live
- The Veterans’ Charity creates spectacular display to honour those lost on 9/11 - Cobseo - The Confederation of Service Charities
- Cancelled GWR trains 'least bad choice' after fleet problems - BBC
- Poppies made of scallop shells honour 9/11 victims in Cornwall - BBC
- Missing man sparks huge coastal emergency search - Cornwall Live
Problems within 7km of Hayle | FixMyStreet
- Trees & bushes in layby obsuring public footpath, 8th September
- Tarmac not holding manhole cover - very noisy, 31st August
- Overgrown footpath which prevens the drop kerb being used for walking aids, wheelchairs and buggies, 25th August
- Crash barrier possibly incorrectly fitted, 25th August
- Large pothole past the farm, 17th August
- Bollard broken, 16th August
Hayle News
- ???? Planning and Transport Committee Meeting
- Road Traffic Regulation Act 1984 S.14: Temporary Prohibition of Traffic
- A post from Hayle Town Council
- a ribbon of poppies for 9/11
- Road Traffic Regulation Act 1984 S.14: Temporary Prohibition of Traffic
- ???? An ???????????????????????????????????? ???????????????????????????? ???????????????????????????? of Hayle Christmas Lights will be taking place on ???????????????????????????????? ???????????????? ???????????????????????????????????? ????:??????????
- Wildanet Streetworks
- Huge thanks to everyone who submitted a vote at the Pool Party to name our lovely dolphin water refill station on King George V ...




Recent comments
32 weeks 1 day ago
37 weeks 1 day ago
37 weeks 1 day ago
1 year 1 hour ago
1 year 19 weeks ago
1 year 19 weeks ago
1 year 19 weeks ago
1 year 19 weeks ago
1 year 41 weeks ago
2 years 3 weeks ago